LAB 3 AGILE SCRUM
AIZATI BINTI AMMAR 01DIS17F1046
NUR SYARAH AFIQAH BINTI YUSAINI 01DIS17F1050
MUHAMMAD AZWAN BIN JOHAN 01DIS17F1031
SITI AIN ZUBAIDAH BINTI SHEIKH AHMAD
NASIR 01DIS17F1007
DFP5043 - Software Requirement and
Design
Lab 3 – Agile Scrum
CLO2
Instruction:
By a group of 4 person, discuss and
answer the question below. Then submit to the class blog.
Q1. Use
Scrum approach to manage the wedding event of yours.
The step involves are,
i.
Name the product owner, scrum master and team
members.
Product Owner: Bride and Groom
Scrum Master: Wedding Planner
Team Members: Catering Team, Wedding Planner Team, Families,
Officiant, Hair Stylist, Makeup Artist, Bridesmaid.
ii.
Create Initial Product Backlog
1. Dowry
2.
Catering
3.
Cake
4.
Bridal Dais
5.
Flower Bouquet
6.
Wedding Band (Ring)
7.
Theme
8.
Location
9. Wedding Invitation
10.
Make Up
11.
Hairstyle
12.
Henna
13.
Date and Time
14.
Budget
15.
Wedding Attires
iii.
List the ideas of whom to do what (user stories) based on Initial Product
backlog
1. 1.
Bride And Groom
·
Set Date and Time
·
Choose Theme and Colors
·
Set Budget
·
Guest List
·
Choose Wedding Attires, Cake Flavor
·
Plan Honeymoon
·
Design Wedding Invitation
·
Finalize Menu
·
Purchase for Dowry
2.
Wedding Planner
·
Manage Bridal Dais
·
Manage Reception Venue
·
Manage Wedding Hall
·
Manage Wedding Dress And Suit
·
Manage Wedding Invitation
·
Arrange Transportation
·
Book Hairstylist, Musician, Caterer, Florist,
Make Up Artist, Cake Baker.
·
Plan the Rehearsal
3.
Florist
·
Manage Flower Bouquet
4.
Caterer
·
Foods and Drinks
·
Dining Table, Chair, Cutlery, Tableware
·
Servers
5.
Bakery
·
Bake Cake and Dessert
6.
DJ Band
·
Make Musician Selection
7.
Photographer/ Videographer
·
Manage Camera Tools Kits
8.
Make Up And Henna Artist
·
Manage Makeup Selection
·
Doing Henna Art
9.
Hairstylist
·
Make Hairstyle Selection
10.
Bridesmaids/ Groomsmen/ Flower Girls
·
Choose Attires based on Theme
·
Rehearsal
11.
Families
·
Manage the Guest List
·
Involves In All Preparation
·
Moral Support
12.
Officiant
·
Conduct Wedding Ceremony
13.
Spa
·
Manicure and Pedicure
·
Massage
14.
Stationer
·
Customized Invitation
15.
Wedding Host
·
Greet Guests
·
Distribute Programs
iv.
Based on user stories, determine the List of Product Backlog by priorities.
1) Work on Budget.
2)
Start the Guest List.
3)
Hire a Planner.
4)
Set Date and Time.
5)
Reserve Venue.
6)
Book and Meet the Officiant.
7)
Research, Hire and Meet the Photographers,
Bands, Florists and Caterers.
8)
Select and Purchase Wedding Invitations,
Wedding Attires, Rings, Dowry.
9)
Arrange Transportation.
10)
Select and Order Cake.
11)
Schedule Henna, Hair and Makeup Artist.
12)
Choose Music.
13)
Finalize Menu.
14)
Spa Treatment.
v.
Planning your List of Sprints and the sprints
duration.
Duration= 4
Weeks
Week 1
1)
Work on Budget.
2)
Start the Guest List.
3)
Hire a Planner.
4)
Set Date and Time.
Week 2
1)
Reserve Venue.
2)
Book and Meet the Officiant.
Week 3
1)
Research, Hire and Meet the Photographers,
Bands, Florists and Caterers.
2)
Select and Purchase Wedding Invitations,
Wedding Attires, Rings, Dowry.
3)
Arrange Transportation.
4)
Select and Order Cake.
Week 4
1)
Schedule Henna, Hair and Makeup Artist.
2)
Choose Music.
3)
Finalize Menu.
4)
Spa Treatment.
vi.
Write an example of what are been discussed in
a.
First Scrum Planning meeting
- describes the highest priority features to the
team. The team asks enough questions that they can turn a high-level user story
of the product backlog into the more detailed tasks of the sprint backlog.
- Estimate the duration to complete backlog item.
b.
Daily meeting
- what each person accomplished yesterday and will accomplish today, the team gains an excellent understanding of what work has been done and what work remains.
- What did you do yesterday?
- What will you do today?
- Are there any impediments in your way?
c.
Review meeting
- shows what they accomplished during the
sprint.
- takes the form of a demo of the new features.
d.
Retrospective meeting
- Start items would be something that the team
would like to add to their process e.g. Start coming on time for project
meetings.
- Stop items would be something that the team no
longer wants to do e.g. stop checking themes without themes review.
- Continue items will be something team wants to
continue doing in future e.g. Continue having daily stand-ups.